Skip to Main Content

Comments and Responses

  • Project Number: N/A
    Date: 08/13/2025
    Location: PO Box 121
    Cross Street: N/A
    Reference Marker: 116
    County: Carbon
    Comment Type: Comment on STIP
    221053 Project Big Creek Section State Highway 230. This section of Highway is very rough. The road won't last until 2032. Most of the winter its the only road to travel between Encampment and Laramie. Large petroleum trucks travel from Walden Area to Sinclair causing even worse damage. Please help!
    RESPONSE
    Thank you for your input. This input has been forwarded on to proper personnel.
  • Project Number: N/A
    Date: 09/04/2025
    Location: 191 N.
    Cross Street: JY Road
    Reference Marker: 5
    County: Sweetwater
    Comment Type: Comment on STIP
    Change the speed of 191 N. from milepost 3 to milepost 5 in both directions to 55 miles per hour. There is a huge increase in traffic getting on and turning off of 191 N in this area. The JY Road has a lot of traffic, getting traffic to slow down to get off to the east side of 191 at the Zip Storage entrance is almost impossible. Not only changing the speed to a slower speed but also by installing orange flags on the new speed signs, and enforcing the change is also necessary.
    RESPONSE
    Thank you for your input. This input has been forwarded on to proper personnel.
  • Project Number: N/A
    Date: 09/17/2025
    Location: Wy-220
    Cross Street: N/A
    Reference Marker: N/A
    County: Natrona
    Comment Type: Project Request
    After all of the construction that was completed on WY-220 (Poplar st), between Collins Dr and Yellowstone, storm drains were never installed. This causes flooding on the southbound lanes any time it rains. They then close a lane so it can be pumped down with, what seems to be, a sump pump. There have been cutouts in the gutters for storm drains, for months now, yet, nothing seems to be happening. I feel like completing a project for improved drainage, should actually improve things, and not make it worse.
    RESPONSE
    Thank you for reaching out with your comments regarding the storm drains on WY-220 (Poplar Street) between Collins Drive and Yellowstone. Due to some unforeseen issues at this location, the completion of the storm sewer including the outfall into the river had to be delayed. The completion of the work is scheduled to resume soon with the contractor mobilizing to the site in early October and the work should be completed by the end of November. Thank you for your patience.
  • Project Number: N/A
    Date: 09/19/2025
    Location: 30th and Bill Nye
    Cross Street: 2461 Overland Rd
    Reference Marker: N/A
    County: Albany
    Comment Type: Comment on STIP
    Hello I am the owner of a large portion of land in Laramie, Albany county. The parcel is between the proposed Bill Nye and 30st connection, as seen on one of the STIP pages and the Laramie master street plan. I can't seem to get a straight answer from anyone in over 20 years. I want to help and be involved if necessary.
    RESPONSE
    The Bill Nye Ave extension you referenced in our STIP is actually a City of Laramie project. WYDOT is involved because the funding used is Federal urban systems dollars that pass through WYDOT to the City. I gather that you may be more curious about a connection of the future 30th street to Bill Nye. I'm unaware of the City's future plans for 30th, they would be the best resource to answer that. For now, I can confirm that there is no connection shown on the plans for Bill Nye. The Bill Nye project schedule is unclear at the moment, the City is working with surrounding landowners to get all the necessary clearances.
  • Project Number: 1104014
    Date: 01/07/2026
    Location: N/A
    Cross Street: N/A
    Reference Marker: N/A
    County: N/A
    Comment Type: Project
    Consider spending money on adding shoulders, even just an extra foot.
    RESPONSE
    We will take a look. Safety and crash history are the first thing we look at when evaluating widened shoulders, and there are other criteria like steep shoulder slopes, bicycle usage, etc. WYDOT has been operating under a Pavement Preservation philosophy for the last ~15 years, so shoulder widenings have been very rare. We will be sure to evaluate the need.
  • Project Number: 1123001
    Date: 01/07/2026
    Location: N/A
    Cross Street: N/A
    Reference Marker: N/A
    County: N/A
    Comment Type: Project
    Add in turn lanes, at least lefts possible a few rights. The area is getting a new subdivision out off the Hillsdale road and traffic will pick up.
    RESPONSE
    You're spot on. There's a lot of commuter traffic and the volumes are quite high for a service road. Our warrant studies identified left turn lanes were needed at the Bar S Trucking approach and at CR 136, and these are currently included on the project. No right turn lanes were identified that I recall. This project has unfortunately been delayed several times as we have had to prioritize our interstate projects, etc. Since it's been a while, we'll be sure to update the counts and warrant studies to make sure we have the right locations for turn lanes. There's been a lot of growth in this area and it seems that trend will only continue.
  • Project Number: I806212
    Date: 01/07/2026
    Location: N/A
    Cross Street: N/A
    Reference Marker: N/A
    County: N/A
    Comment Type: Project
    This doesn't seem justified. The rest of I80 and other roads are falling apart, or in need of additional lanes. This seems like a "show me" project that doesn't need to be done.
    RESPONSE
    This is a huge project for sure, and I agree the list of needs on the rest of our highways only continues to grow. We do feel this interchange replacement is a need and replacing it will have real, lasting benefits. We're also aware it can't come at the expense of the rest of our system. So far we've funded the vast majority of the design with grants that are separate from our "normal" highway funding program. I anticipate the construction funding will be a similar situation whenever that day comes. It's an issue we're evaluating carefully, all the way up to WYDOT's senior leadership. The need for this interchange has been studied for a long time. The justifications are both safety and capacity related, and have mostly to do with the tight cloverleaf ramp configuration of the existing interchange and the close proximity of the smaller service interchanges nearby. There's a lot going on in a very small area, and the problems we see will continue to worsen. The existing bridge
  • Project Number: N561044
    Date: 01/07/2026
    Location: N/A
    Cross Street: N/A
    Reference Marker: N/A
    County: N/A
    Comment Type: Project
    Make this a five lane road continued from the previous section. Add some intersection lighting at the intersections with higher use.
    RESPONSE
    We do have a 5-lane designed and ready to go. Originally, our 2024 US 30 project went from Pershing to Archer and would have included this segment. Unfortunately we had to split the project in two due to cost. The traffic volumes on this second segment are quite a bit less than the first piece. By the numbers, we're not over capacity yet and may not be for quite a while. I anticipate this project will be on standby until we can secure funding for capacity improvement projects. We did look at intersection lighting and will update that as traffic volumes increase. Similar to signals, we have warrant criteria we stick to to justify these installations. Lighting is a big safety benefit for rural intersections, so we'll be sure to keep evaluating it.
  • Project Number: U212021
    Date: 01/07/2026
    Location: N/A
    Cross Street: N/A
    Reference Marker: N/A
    County: N/A
    Comment Type: Project
    There needs to be left turn arrow for people trying to turn left off of College on to east I80 and from the west I80 onto college. It is getting to be long waits at almost anytime (besides midnight)
    RESPONSE
    Delays for these two movements are high during peak periods, I agree. We have looked at both situations, a new signal at the westbound off ramp and a left turn phase for southbound College to eastbound I-80. Based on our most recent counts, both of these movements are still short of the traffic volumes needed to satisfy our minimum warrant criteria. We will definitely keep an eye on the delays and update our counts to see where we are. Closely spaced traffic signals create their own set of problems, and that's why we're careful to hold off until warrants are met before making changes. Especially in this location. Thru traffic volumes on this segment of College Drive are some of the highest in the State. We'll watch it closely. We are adding a dual left turn lane off the I-80 eastbound ramp to NB College on this project to eliminate the ramp backing up onto I-80. This may allow us to allocate some additional signal time to the other movements which might help some.